Harmony (Eva Copper Mine Pty Ltd) has lodged an application for a major amendment to an Environmental Authority in accordance with the requirements of the Queensland Environmental Protection Act 1994. The Environmental Authority being amended is EPML00899613.
The amendment application relates to the Eva Copper Mine Project (the Project) located 75 km north of Cloncurry town and 95 km north-east of Mount Isa.
The amendment application seeks to update EPML00899613 to align with changes to the Life of Mine Plan, based on the Project’s updated Feasibility Study. Key amendments include an extended mine life, increased extraction and processing capacities, expanded disturbance footprint, additional Environmentally Relevant Activities, revised water management systems, and updated water supply sources and demand.
This website provides access to information and documents relevant to the amendment application.
The amendment application was open for public comment from Thursday 5 February 2026 to Friday 6 March 2026 (inclusive – Queensland time).
With the public notification period completed, the Department of the Environment, Tourism, Science and Innovation is now deciding on the amendment application.
The documents related to this application are available on this webpage.
Find out more
For general information about the project or the application (not submissions), contact.
07 4442 2211
Eva Copper Community Hub
47 Ramsay Street Cloncurry Queensland
4824 Australia
List of documents
Statutory Notices
Information Request Response submitted January 2026
- Cover letter
- Eva Copper Mine Project – Feasibility Study Alignment Environmental Assessment Report
- Appendix A – Statutory Compliance Tables
- Appendix B – Environmental Risk Assessment
- Appendix C – Ecology Impact Assessment
- Appendix D – Matters of State Environmental Significance Impact Areas
- Appendix E – Groundwater Impact Assessment
- Appendix F – Surface Water Impact Assessment
- Appendix G – Noise and Vibration Impact Assessment
- Appendix H – Air Quality Impact Assessment
- Appendix I – Geochemical Characterisation
- Appendix J – Greenhouse Gas Assessment
- Appendix K – Engagement Register
- Appendix L – Environmental Authority Mark-up
Original Application Material submitted May 2025
- Eva Copper Mine Project – Feasibility Study Alignment Environmental Assessment Report
- Appendix A – Statutory Compliance Tables
- Appendix B – Environmental Risk Assessment
- Appendix C – Ecology Impact Assessment
- Appendix D – Matters of State Environmental Significance Impact Areas
- Appendix E – Groundwater Impact Assessment
- Appendix F – Surface Water Impact Assessment
- Appendix G – Noise and Vibration Impact Assessment
- Appendix H – Air Quality Impact Assessment
- Appendix I – Geochemical Characterisation
- Appendix J – Greenhouse Gas Assessment
- Appendix K – Environmental Authority Mark-up